Construction on the LHWA GAC plant began in March 2007.  

The first full day of GAC plant operation was November 2, 2007.

The GAC Plant is currently removing C-8 from our drinking water down to undetectable levels.  (Refer to “Sampling Results”.)

On June 14, 2010 the GAC plant had its fourteenth GAC changeout.